Progress billing is billing a job in parts as the work gets done, instead of in one bill at the end. Each part bill covers a stage or a share of the work. The last one bills what's left.
It's week three of a five-week job. You've bought the equipment, paid the crew twice and pulled the permit. The client hasn't paid since the deposit, because the deal was "the rest when it's done."
Below I cover when to bill in parts, three ways to split a job, what every part bill should show, retainage, the AIA forms, and the state rules to check. One example job runs through every section.
The example job. An HVAC shop installs heating and cooling in a home addition for the Pendletons, the homeowners. The price is $24,000, fixed, and the work runs about five weeks. Every figure for this job is an example, not a statistic.
What is progress billing?
Progress billing means you bill for the work done so far, at points set in the contract, rather than all at the end. The client pays each part bill as it comes. The final bill takes off everything billed before it.
It goes by other names: progress invoicing, progress payments, draws. On commercial work, each request is often called a pay application. It suits jobs that run for weeks, where your costs come long before the last day.
When to bill in parts, and when a deposit and final bill are enough
Most small jobs don't need it. For a furnace swap, a bath fan or a day of repairs, a deposit at signing and one bill at the end cover it.
Bill in parts when one of these is true:
- The job runs longer than your payroll. If you pay the crew every week, a five-week job means five payrolls before the last bill.
- The materials cost a lot up front. The deposit pays for the order. The next bill pays for the labor going in.
- The work has stages anyone can see. Rough-in done, roof dried in, cabinets set.
- The client pays on a schedule. A builder or general contractor will tell you how they want to be billed.
The deposit and the part bills do different jobs. The deposit pays for the start: the order, the permit, the first days. The part bills keep money coming in step with the work. Taking the deposit, sending each bill and chasing the ones paid late are in our construction invoicing guide. This guide stays on the part bills.
Put the split in the contract before the first bill: each bill's amount or percent, what triggers it, and when it's due. A client who agreed to a bill in writing expects it. Some states cap the down payment on a home improvement job. California caps it at $1,000 or 10 percent of the price, whichever is less, and no later bill may run ahead of the work done and materials delivered (the state license board's bulletin on payment limits). Check your state's rule before you set the deposit.
Three ways to split a job
Of the three common ways to split a job, a small shop usually bills by stage. The other two show up on larger jobs, and when a general contractor sets the terms.
1. By stage
Each bill is tied to a stage of the work, with a set percent or amount. When the stage is done, the bill goes out. Here is the example job split by stage.
| Bill | When it goes out | Share | Amount |
|---|---|---|---|
| Deposit | At signing | 25% | $6,000 |
| Rough-in done | Ductwork and line set in, before drywall | 35% | $8,400 |
| Equipment set | Heat pump and air handler set and connected | 25% | $6,000 |
| Final | After startup and inspection | 15% | $3,600 |
| Total | 100% | $24,000 |
Stage bills are the easiest for a homeowner to follow. They can see the ductwork before they pay for it. Keep the last bill big enough to matter, so the punch list gets finished.
How JobsiteBooked does this: a part bill is a name and an amount or a percent of the job total, so this one is "Rough-in done, 35%." We built the percents to come out even. Bill 25%, 25% and 50%, and Left to invoice ends at exactly $0, never a cent over.
2. By percent done
At set times, often each week or each month, you judge what share of the work is finished. You bill that share of the price, less what you've billed already.
Example: at the end of week two, the job looks 40 percent done. 40 percent of $24,000 is $9,600. Less the $6,000 deposit, this bill is $3,600.
This follows the work closely, but the percent is a judgment call. Write into the contract how it's judged, and expect the client to ask.
In JobsiteBooked, you work out the amount and type it into the part bill.
3. By schedule of values
A schedule of values breaks the price into lines, each with its own value. Each bill shows how much of each line is done. Builders and commercial owners often ask for it, because it shows what they're paying for.
Example: the job's schedule of values, and the count at the end of week two.
| Line | Value | Done | Earned to date |
|---|---|---|---|
| Heat pump and air handler | $9,600 | 0% | $0 |
| Ductwork and registers | $7,200 | 75% | $5,400 |
| Line set, drain and hookups | $3,600 | 50% | $1,800 |
| Thermostat and controls | $1,200 | 0% | $0 |
| Permit and inspection | $1,200 | 50% | $600 |
| Startup and balancing | $1,200 | 0% | $0 |
| Total | $24,000 | $7,800 |
Earned to date is $7,800. Less the $6,000 billed before, this bill is $1,800.
The count by line says the job is about a third done, not the 40 percent a quick look gave. That gap is why builders ask for it.
Pick the method by who's paying. A homeowner gets stage bills. A builder who sends their own pay form gets a schedule of values.
What every part bill shows
Before the client asks how far along the job is, the part bill should already say. Four numbers do that. Keep them apart on every bill.
| Number | What it means |
|---|---|
| This bill | What you're asking for now |
| Billed so far | Every bill to date, this one included |
| Paid so far | What the client has paid to date |
| Left to bill | The job total, less billed so far |
In an early test of our own billing screen, I put 25% down on a job. The screen still showed the full job total left to invoice, and I couldn't see how to ask for the deposit. Now the deposit has its own line on the job's Billing card.
Here is the example job, bill by bill. In week four the Pendletons add an extra supply run to the bonus room, a $1,200 change order.
| Bill | This bill | Billed so far | Paid so far when sent | Left to bill after |
|---|---|---|---|---|
| Deposit | $6,000 | $6,000 | $0 | $18,000 |
| Rough-in done | $8,400 | $14,400 | $6,000 | $9,600 |
| Equipment set | $6,000 | $20,400 | $14,400 | $3,600 |
| Change order: extra supply run | adds $1,200 to the job | $20,400 | $20,400 | $4,800 |
| Final | $4,800 | $25,200 | $20,400 | $0 |
A few more lines belong on every part bill:
- What it covers, in words. "Rough-in done", not "Bill 2".
- The job total, with any change orders that raised it.
- The due date and how to pay.
- Retainage, if the contract holds it: the amount held on this bill and in total.
The final bill lists every earlier bill and what each one paid. The client sees how the last number was reached, with nothing to work out.
In JobsiteBooked, every invoice made from a job carries the line "Job total · Invoiced before · This invoice · Left to invoice after", with the amounts filled in. Every bill gets the next number, your logo and the client's own terms.
Billing the example job in JobsiteBooked, step by step
Here is the Pendleton job in JobsiteBooked's contractor invoicing software. Part bills work on a fixed-price job, or a job made from an estimate.
- The client signs and pays the deposit. The Pendletons sign the estimate on their phone and pay the 25 percent deposit by card. The job appears by itself, and its Billing card says Deposit paid.
- Bill the rough-in. On the job's Billing card, press Bill part of this job. Name it "Rough-in done", enter 35 percent and press Make part invoice. Open it from the Billing card and text it, email it, or both. A part bill can't go past what's left to invoice.

- Bill the equipment. When the heat pump is set, press Bill part of this job again: "Equipment set", 25 percent. Left to invoice drops each time.
- Add the change order. The Pendletons ask for the extra supply run. You or the office open the job's lines on the phone app and press Change order. The Pendletons sign it from its link, and the job total and Left to invoice rise by $1,200.
- Invoice the rest at the walkthrough. After startup and inspection, Invoice the rest bills the last $4,800. The deposit and both part bills are listed as taken off, each marked Paid, Part paid or Not paid yet. Left to invoice reads $0.

- The client pays. The Pendletons pay each bill from its own link: by card (on a phone, Google Pay and Apple Pay work too), or by bank once you switch bank payments on. No card fee is added. A receipt goes back by text and email by itself, and an unpaid bill gets reminders.
On the phone, the job's money card sums it up: the amount due, what's billed and not paid, and what's not billed yet. One bar holds all three, so the whole job reads at a glance.

Retainage: the part held back
Retainage, also called retention, is a share of each payment the client holds back until the job is done. It's the client's cover if the work isn't finished or put right. It's rare on a homeowner job. Between an owner and a general contractor, and between a general contractor and its subs, it's common.
Example: with 5 percent retainage, the $8,400 rough-in bill shows $420 held and $7,980 due now. Across the whole $24,000 job, $1,200 is held. It's paid at the end, once the contract's terms are met.
Three habits keep retainage from going missing:
- Write the terms into the contract. The percent, what "done" means, and how many days after that the held money is due.
- Show it on every bill. Retainage held on this bill, and in total.
- Bill it when the job is done. Send the held amount as its own bill, the day the terms are met. It rarely arrives unasked.
How much can be held, and how fast it's paid back, is set by the contract and by state rules. The rules section below has them.
AIA G702 and G703, in short
On a commercial job, a general contractor may ask you to bill on AIA forms. AIA is the American Institute of Architects, which publishes standard construction contracts and forms.
- G702 is the Application and Certificate for Payment. You ask to be paid, and the architect certifies the amount due.
- G703 is the continuation sheet. It breaks the contract sum into lines, your schedule of values, and backs up the G702.
If you've billed by schedule of values, the G703 holds the same lines. When a contract calls for them, use the forms it names.
Progress billing rules: retainage caps and prompt payment
Your contract sets most of the terms. State law sets limits the contract can't go past, and they differ by state and by kind of job. These are the rules we read. Check your state's rule before you set yours.
| Rule | What it says |
|---|---|
| Federal jobs, retainage | Held only when progress isn't satisfactory, and at most 10 percent of the approved estimated amount |
| Federal jobs, paying the prime | 14 days after a proper payment request reaches the billing office |
| Federal jobs, paying the subs | Within 7 days of the prime being paid |
| California, private work | At most 5 percent of each payment and of the contract, at every tier from owner down to sub, for contracts from January 1, 2026, unless a bond was required in the bid request. Residential work of four stories or less, not mixed-use, is outside the cap |
| California, release | An owner who holds back retention from a direct contractor pays it within 45 days after the work is complete, with exceptions for public-entity acceptance and a good-faith dispute |
| Washington, private work | At most 5 percent of the price of completed work. Single-family residential construction under 12 units is outside it |
| Texas, private work | Not a cap: the owner holds back 10 percent of the contract price or of the value of the work done, during the work and for 30 days after completion |
Federal jobs. Under the federal rule on retainage, a contracting officer may hold it only when progress isn't satisfactory, and at most 10 percent of the approved estimated amount. The rule says retainage shouldn't stand in for good contract management. The federal prompt payment clause pays a progress payment 14 days after a proper request arrives. The prime then pays its subs within 7 days of being paid, and late payments to subs carry interest.
California. For private contracts entered on or after January 1, 2026, Civil Code 8811 caps retention at 5 percent of each payment and of the contract price, at every tier from owner down to sub, unless a bond was required in the bid request. Residential projects of four stories or less that aren't mixed-use are left out. Under Civil Code 8812, an owner who holds back retention from a direct contractor pays it within 45 days after the work is complete, with exceptions for public-entity acceptance and a good-faith dispute.
Washington. RCW 60.30.010 limits retainage on private work to 5 percent of the price of completed work. Single-family residential construction under 12 units is outside it, so read the rule for your job.
Texas. Property Code 53.101 works the other way. The owner must hold back 10 percent of the contract price or of the value of the work done, during the work and for 30 days after completion. Read the current text.
Every other state. Retainage caps and prompt payment deadlines differ, for public and private work. Check your state's rule, and your contract, before the first bill goes out.
Progress billing in QuickBooks Online
QuickBooks Online has progress invoicing of its own. Per Intuit's help page, you turn it on in the Sales settings. Then you invoice from an estimate: the whole amount, a percent, or chosen lines. The Estimates and Progress Invoicing Summary by Customer report shows each estimate's total, what's invoiced and what's left. Check that your plan has it.
If you bill from JobsiteBooked, the QuickBooks sync sends each bill to QuickBooks Online once it leaves draft: the deposit, every part bill and the final. Each payment goes in applied to its bill, in Undeposited Funds, and refunds go in as refund receipts. The sync runs one way, so nobody types a part bill twice. Lines go in under one sales item you choose.
Where these rules come from: the federal acquisition rules, the California, Washington and Texas codes, and the AIA and Intuit pages linked where they come up, as of November 27, 2026. The screens are from JobsiteBooked.

Eric Scarfo
Eric Scarfo is co-founder of JobsiteBooked, business software for U.S. trade shops. He studies how trade businesses document their work, from the first look at a job to the final bill.